LNG Canada申请把Kitimat设施合并例行火炬燃烧限额提高至现有约9.75倍。公司称早期运营及一处燃烧头故障令2025年至2026年初燃烧量超出许可,并表示过去六个月已减少40%、正改进设备。申请尚不能视为获准。

公司称更新的空气扩散模型及健康风险评估支持申请,当地空气质量健康指数维持良好或低风险,预计调整不会显著增加当地空气域排放。SFU及UBC的健康专家则担忧挥发性有机物、苯及既有心肺疾病者风险,并指出气象会影响暴露,燃烧量增加与居民暴露不是简单一比一。

卑诗绿党要求先做全面健康评估;研究者通过信息公开获得超许可燃烧资料,也引发透明度质疑。报道另提Woodfibre LNG空气许可及实时监测争议,两者是不同设施。能源监管机构因选后过渡期未作评论。

来源:CBC News 原报道。大鱼新闻整理原创中文摘要;保留原刊发日期。

A flare is seen at the LNG Canada plant in Kitimat, B.C., in April 2025 as the facility begins pre-operational work. LNG Canada has applied to increase its flare limit about tenfold. (Chris Corday/CBC)

A flare is seen at the LNG Canada plant in Kitimat, B.C., in April 2025 as the facility begins pre-operational work. LNG Canada has applied to increase its flare limit about tenfold. (Chris Corday/CBC)

Tim Takaro, planetary health lead at SFU’s school of medicine, says there is a reason the flaring limits are set the way they are. (Maggie MacPherson/CBC)

Tim Takaro, planetary health lead at SFU’s school of medicine, says there is a reason the flaring limits are set the way they are. (Maggie MacPherson/CBC)

Woodfibre LNG is under construction at the site of the old pulp mill about seven kilometres southwest of Squamish. (Alanna Kelly/CBC)

Woodfibre LNG is under construction at the site of the old pulp mill about seven kilometres southwest of Squamish. (Alanna Kelly/CBC)